Keeping Pebble Creek safe and beautiful. This page tracks current and recently completed maintenance projects in our neighborhood.
Sidewalk Repair โ 1st Location
Culvert hole identified and sealed with concrete backfill. New sidewalk panel poured.
๐ข Complete โ Apr 22, 2026Sidewalk Repair โ 2nd Location
Same culvert erosion issue discovered at a second drain location. Drain filled and concrete poured same day.
๐ข Complete โ Apr 26, 2026Street Repaving
HOA Board has contacted the City of Shelby requesting a timeline for black-topping Pebble Creek streets.
๐ก In Communication โ Apr 22, 2026Entrance Trees & Shrubs
Grant's Tree Service trimmed 38 Crepe Myrtle trees and 13 Holly clusters at the neighborhood entrance. All debris removed.
๐ข Complete โ Mar 17, 2026Curb Maintenance โ 737 Cedar Hill Dr
City of Shelby confirmed curb repair is on the city repair list. Repair anticipated within ~2 months pending ADA ramp work.
๐ก Scheduled โ Apr 30, 2026Lawn Care โ Spring & Summer
A reminder from the Board to mow, edge, trim, and weed regularly. Let's keep Pebble Creek looking its best this season.
๐ฑ Action Requested โ May 2026